    Codelco’s El Teniente setback: seismic risk and supply impacts for mine planners

    August 5, 2026|

    Reviewed by Joe Ashwell

    Codelco’s El Teniente setback: seismic risk and supply impacts for mine planners

    First reported on MINING.com

    30 Second Briefing

    Suspended development of the Andes Norte section at Codelco’s El Teniente, triggered by new studies of an “emerging seismic phenomenon” at greater depth, may last up to two years and follows a July 2025 rockburst equivalent to magnitude 4.2 that killed six workers in adjacent Andesita and Teniente 7 panels. El Teniente’s output is already about 27% lower year-on-year and Codelco has conceded its 1.7 Mt/y copper target for 2030 is unattainable, tightening a market where CRU reports one LME participant holding 50–79.99% of live copper warrants. Comex September copper hit an intraday record of $6.7045/lb as Chile posted its weakest Q2 copper production in nearly 20 years, with traders diverting metal into the US ahead of possible tariffs.

    Technical Brief

    • Six-month geotechnical review at Andes Norte identified a new deep-level seismic mechanism unlike historically managed hazards.
    • The July 31, 2025 rockburst in Andesita and Teniente 7, magnitude-4.2 equivalent, triggered criminal, regulatory and technical investigations.
    • Suspension of Andes Norte development for up to two years is explicitly framed as a worker-safety protection measure, not an economic optimisation.
    • The emerging seismic phenomenon is described as depth-related, implying possible transition from structurally controlled to stress-driven failure regimes.
    • Similar deepening projects globally are being cautioned that conventional rockburst controls may be insufficient once operations push into comparable stress domains.

    Our Take

    In our database, Codelco already features heavily in recent copper price coverage, and the El Teniente setback compounds a pattern where Chilean supply issues are repeatedly cited alongside tight LME warrant control and record Comex levels above $6.60/lb.

    The suspension at the Andes Norte section lands just as Codelco is also delaying its Maricunga lithium project to 2034, signalling that Chile’s state miner is simultaneously under strain in both copper and lithium build‑outs rather than being able to lean on battery metals growth.

    With El Teniente output already at a 25‑year low and Codelco publicly shifting to ‘profitability over volume’ in July 2026, high‑cost or geotechnically complex copper expansions in the Andes are likely to face tougher internal hurdle rates, which could open space for lower‑risk producers such as Freeport‑McMoRan and Southern Copper highlighted in other recent copper price pieces.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Gold price slides on strong dollar: planning implications for mine projects
    Mining
    about 16 hours ago

    Gold price slides on strong dollar: planning implications for mine projects

    Gold prices slipped to a one-week low as spot gold fell 0.4% to $4,271.16/oz in New York and December futures eased 0.3% to $4,306 amid a stronger US dollar and expectations of more hawkish US Federal Reserve rate moves. The dollar hit a two-month high and US 10-year Treasury yields hovered near a 20-year peak, sharply raising the opportunity cost of holding non-yielding bullion. Oil gained about 1% on stalled US–Iran talks over the war, while spot silver dropped 1.8% to $63.29/oz, platinum 0.2% to $1,746.44, and palladium rose 0.5% to $1,266.40.

    OceanaGold Waihi expansion: design, throughput and tailings notes for engineers
    Mining
    about 16 hours ago

    OceanaGold Waihi expansion: design, throughput and tailings notes for engineers

    OceanaGold is weighing a 50% expansion of its Waihi plant to 1.2 Mt/y after Wharekirauponga drilling returned standout intercepts including 6.3 m at 97.2 g/t Au from 481.5 m in the East Graben vein and 8.5 m at 41.5 g/t from 399 m. The move would enable concurrent feed from Martha Underground and Wharekirauponga post‑2032, building on a 2024 plan outlining 1.6 Moz over 15 years and an initial 4.1 Mt reserve at 9.2 g/t. Underground development is advancing, with the Waihi North decline now 350 m, first vent shaft under construction, staged commissioning of a new water treatment plant, and early works on a new tailings storage facility due in Q4.

    Kinross Gold output cut and higher AISC: operational drivers and FCF lens for mine teams
    Mining
    about 17 hours ago

    Kinross Gold output cut and higher AISC: operational drivers and FCF lens for mine teams

    Kinross Gold has cut its 2026–27 production outlook by about 8% to 1.84–1.86 million attributable gold-equivalent oz. a year and raised 2024 AISC guidance to $1,850–$1,900/oz after winter storms, copper-rich sulphide ore and poor recoveries at La Coipa in Chile, plus weaker mining rates, grades and recoveries at Round Mountain Phase S in Nevada. The company is stockpiling high-copper material, studying a new flotation circuit for deeper sulphide mineralisation that may overlie a copper porphyry system, and using a smaller shovel at Round Mountain to cut dilution. Despite the operational hit and a Q3 output cut to about 425,000 oz., Kinross has lifted its 2026 shareholder return target to 50% of free cash flow and has already returned about $800 million this year, mainly via $655 million in buybacks.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.