    £100k fine for temporary works fail: critical lessons for site engineers

    December 17, 2025|

    Reviewed by Tom Sullivan

    £100k fine for temporary works fail: critical lessons for site engineers

    First reported on The Construction Index

    30 Second Briefing

    A newly built breeze block retaining wall collapsed into a deep excavation on Old Coast Guard’s Road, Poole, crushing 69-year-old steel-fixer Patrick Grant and prompting a £100,000 fine for principal contractor Matrod Frampton Limited. HSE found the wall had been backfilled before the mortar had set, there was no temporary works design for the wall or other structures, and no temporary works co-ordinator or supervisor had been appointed despite a safety report warning eight days earlier. Rescue was further delayed by reliance on an unstable ladder and the absence of an excavation emergency plan.

    Technical Brief

    • Failure mechanism: unreinforced breeze block wall in deep excavation overloaded by premature backfill before mortar gained strength.
    • HSE investigation focused on absence of any formal temporary works design for the blockwork wall or other supports.
    • No temporary works co-ordinator or supervisor had been appointed, despite this being raised in a safety report eight days earlier.
    • Incident occurred at around 8:30am on 19 August 2022 at Old Coast Guard’s Road, Poole.
    • Access to the excavation relied on an unstable ladder, introducing secondary fall and rescue hazards.
    • Rescue required hoisting the injured worker by fire and rescue services and subsequent airlifting to hospital.
    • Bristol Magistrates’ Court recorded breaches of CDM 2015 Regulations 13(1) and 19(1) by Matrod Frampton Limited.
    • Sentencing included a £100,000 fine, £8,242 costs and a £2,000 victim surcharge, reinforcing CDM enforcement expectations.
    • For similar excavations, robust temporary works procedures, early design sign-off and rehearsed excavation emergency plans are critical controls.

    Our Take

    Among the 16 Hazards stories in our coverage, UK cases involving the Health & Safety Executive (HSE) often lead to six‑figure penalties, signalling that even medium-sized contractors like Matrod Frampton face material financial exposure when temporary works design and supervision are inadequate.

    The eight‑day gap between a safety report and the wall collapse fits a recurring pattern in our safety-tagged pieces where early warnings are logged but not escalated into formal design checks or method revisions, suggesting firms need clearer triggers for independent review of temporary works in urban refurbishment jobs.

    Incidents in residential or mixed-use settings such as Riverside Park in Dorset tend to attract more scrutiny in our database than comparable failures on closed industrial sites, which likely means contractors in UK towns like Poole and Wimborne will see client and insurer pressure for more rigorous temporary works sign-off and competence records.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Melbourne sinkhole investigations: geotechnical lessons for tunnel project teams
    Hazards
    in 5 months

    Melbourne sinkhole investigations: geotechnical lessons for tunnel project teams

    A sinkhole roughly 8–10 m wide and several metres deep has opened on the AJ Burkitt Reserve sporting oval in Heidelberg, directly adjacent to the North East Link tunnel alignment in Melbourne’s northeast. Victorian Infrastructure Delivery Authority has confirmed the “surface hole” is in the vicinity of active tunnelling operations, leading to a work pause while engineers and emergency crews carry out geotechnical investigations and monitoring. No injuries or structural damage have been reported, but the area remains fully cordoned off pending cause determination and stability assessment.

    Spain retaining wall collapse derailment: failure lessons for rail engineers
    Hazards
    2 days ago

    Spain retaining wall collapse derailment: failure lessons for rail engineers

    A commuter train derailed in Gelida, near Barcelona, on 20 January after striking a collapsed retaining wall that had fallen onto the track, killing the driver and injuring 37 passengers. The incident, Spain’s second fatal rail accident in a week, occurred on a section of line with trackside earth-retaining structures, raising immediate questions over wall design, drainage, inspection frequency and slope stability under recent weather conditions. For civil and geotechnical engineers, failure mode identification and rapid condition assessment of similar retaining systems on active corridors will be a priority.

    Thailand crane collapse on passenger train: engineering lessons for rail projects
    Hazards
    10 days ago

    Thailand crane collapse on passenger train: engineering lessons for rail projects

    A construction crane collapsed onto a moving passenger train in northeastern Thailand on Wednesday morning, killing at least 32 people and injuring more than 60. The crane, operating on an adjacent construction site, failed and toppled across active railway tracks, striking multiple carriages at speed and causing extensive structural damage and derailment. Investigators are expected to focus on crane foundation design, ground conditions near the rail corridor, lift planning, exclusion zones and compliance with Thai standards for plant operating beside live transport infrastructure.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    Tunnelling

    Specialised solutions for tunnelling projects including grout mix design, hydrogeological analysis, and quality control.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.