    Liberty Gold’s Black Pine FAST-41 approval: capex and permitting lens for mine planners

    January 21, 2026|

    Reviewed by Tom Sullivan

    Liberty Gold’s Black Pine FAST-41 approval: capex and permitting lens for mine planners

    First reported on MINING.com

    30 Second Briefing

    Liberty Gold’s past-producing Black Pine oxide gold project in southeastern Idaho has been accepted into the US FAST-41 “covered project” programme, giving it a federal permitting timetable, project advisor and public dashboard schedule to be set within 60 days. The brownfield, drive-in/drive-out operation near the Utah border hosts 402.6 million tonnes indicated at 0.32 g/t Au (4.16 Moz) plus 97.7 million tonnes inferred at 0.23 g/t Au (0.71 Moz), with a 2024 PFS outlining 2.2 Moz over 17 years at $1,380/oz AISC and $327 million initial capex. Using $2,000/oz gold and a 5% discount rate, the study shows a post-tax NPV of $550 million and 32% IRR, with feasibility-level engineering and environmental baseline work already under way.

    Technical Brief

    • FAST-41 “covered project” status assigns a federal project advisor to coordinate inter-agency permitting for Black Pine.
    • A detailed federal permitting timetable must be agreed and posted to the public dashboard within 60 days.
    • Ongoing work includes feasibility-level engineering, concurrent with both state and federal permitting processes.
    • Environmental baseline studies are already “extensive” and continuing, supporting the brownfield permitting narrative.
    • Black Pine is operated as a drive-in/drive-out site, about two hours by road from Salt Lake City.
    • No permanent camp is planned; the sparsely populated area still allows year-round site access.
    • Market reaction to the FAST-41 news lifted Liberty Gold’s share price 7.7% to C$1.05, valuing it at ~C$537 million.

    Our Take

    With an after-tax NPV of $550 million against initial capital of $327 million, Black Pine screens as a relatively high-margin US gold project in our database, which may make Liberty Gold a more likely takeover or JV target compared with peers with thinner economics.

    The 17-year mine life on 0.32 g/t indicated material at Black Pine fits a pattern in our gold coverage where US heap-leach style projects are increasingly optimised around large, low-grade tonnages rather than chasing higher grades, which has implications for permitting footprints and long-term water management in Idaho.

    Among the 697 Mining stories in our database, only a subset of US gold projects show a 30%+ after-tax IRR at a 5% discount rate, so Liberty Gold’s share price move and C$537 million market value suggest investors are already pricing in a higher probability that FAST-41 support will translate into de-risked development this year’s second half.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Mining
    about 4 hours ago

    Fluor and WSP on USA Rare Earth’s Round Top: design and risk notes for mine teams

    USA Rare Earth Inc has appointed Fluor Corp and WSP Global Inc as EPCM partners to advance the definitive feasibility study for its Round Top rare earth project in Texas, targeting heavy rare earths and critical magnet materials. The mandate covers process plant, mine infrastructure and associated large-scale infrastructure delivery, drawing on Fluor’s mining and processing design capability and WSP’s experience in complex project execution. For geotechnical and civil teams, early EPCM involvement signals imminent definition of pit design, waste storage, haul roads and water management concepts ahead of permitting and financing.

    Mining
    about 5 hours ago

    CIMIC–Hindustan Zinc tailings recycling project: design notes for mine engineers

    CIMIC Group subsidiaries Sedgman and Leighton Asia have secured separate contracts from Hindustan Zinc Limited to help deliver India’s first zinc tailings recycling facility at the Rampura Agucha Mine in Rajasthan. Sedgman will focus on process plant and tailings treatment infrastructure, while Leighton Asia will provide project delivery and construction services for the brownfield site. The project signals large-scale reprocessing of legacy zinc tailings at one of the world’s largest zinc operations, with implications for paste backfill design, tailings storage stability and metal recovery circuits.

    Argent high-grade silver and peers: exploration takeaways for mine planners
    Mining
    about 13 hours ago

    Argent high-grade silver and peers: exploration takeaways for mine planners

    Exploration activity across Australia this week includes Argent Minerals reporting high-grade silver intercepts at its Kempfield project in New South Wales, with mineralisation extending along strike from existing volcanogenic massive sulphide-style resources. Kalamazoo Resources advanced drilling at its gold targets in the Pilbara and Central Victorian Goldfields, focusing on structurally controlled lodes near historic workings and testing down-dip extensions below old stopes. Adelong Gold continued resource-definition work at the Adelong project in NSW, targeting shear-hosted quartz veins to upgrade JORC classifications and refine pit and underground designs.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.