    New Pacific Metals’ Carangas PEA update: economics and mine plan notes for engineers

    July 22, 2026|

    Reviewed by Tom Sullivan

    New Pacific Metals’ Carangas PEA update: economics and mine plan notes for engineers

    First reported on MINING.com

    30 Second Briefing

    New Pacific Metals has updated the PEA for its Carangas silver-gold-zinc-lead project in Bolivia, outlining a 19-year life of mine (plus two years’ pre-production) with total output of 195 Moz payable silver, 1.1 Moz gold, 1,453 Mlb zinc and 941 Mlb lead (339 Moz AgEq). The study gives a post-tax NPV of $3.23 billion and IRR of 37.0% at $5,100/oz gold, with initial capex of $644.5 million, LOM capex of $1.2 billion and a 2.4-year payback. Average AISC is $18.25/oz AgEq, with silver-dominant production of 15.5 Moz/year in years 1–8 before transitioning to 7.6 Moz Ag and 142.7 koz Au per year in years 9–16.

    Technical Brief

    • Updated PEA increases plant throughput and explicitly incorporates the separate gold zone into mine planning.
    • Base-case economics assume $45/oz Ag, $3,400/oz Au, $1.20/lb Zn and $0.90/lb Pb.
    • Upside case at $67.50/oz Ag (other metals constant) yields $16 billion NPV and 51.5% IRR.
    • Ore extraction is scheduled only in years 1–16, with years 17–19 fed entirely from stockpiles.
    • Pre-gold period AISC is $12.11/oz Ag net of by-product credits, indicating strong early cash margins.
    • Growth capital totals $422.7 million and sustaining capital $166.5 million within the $1.2 billion LOM capex.
    • Closure expenditure is estimated at $149.8 million, implying substantial allowance for rehabilitation and long-term care.

    Our Take

    With initial capital costs of about US$644.5 million and a post-tax payback of 2.4 years, Carangas sits in the upper tier of Latin American silver-gold projects in our database in terms of capital intensity but compensates with unusually rapid capital recovery, which can be attractive to lenders in a jurisdiction like Bolivia.

    The inclusion of Cobre Panama’s 2023 shutdown in the key metrics underlines how large-scale closures elsewhere in Latin America can tighten regional concentrate treatment capacity, which may influence offtake terms for Carangas’ lead and zinc by-products over its 19-year life-of-mine.

    Geotechnical Software for Modern Teams

    Centralise site data, logs, and lab results with GEODB-io, CMRR-io, and HYDROGEO-io.

    No credit card required.

    • Save and export unlimited calculations
    • Advanced data visualisation
    • Generate professional PDF reports
    • Cloud storage for all your projects

    Prepared by collating external sources, AI-assisted tools, and Geomechanics.io’s proprietary mining database, then reviewed for technical accuracy & edited by our geotechnical team.

    Related Articles

    Mining
    about 6 hours ago

    Glencore’s US$250m Cat order for Alumbrera: fleet renewal lens for mine planners

    Glencore has placed a US$250 million order with Finning’s South America business to supply more than 20 large Caterpillar mining trucks, ancillary equipment and technology support for the planned 2026 restart of the Alumbrera copper mine in Argentina. The package, disclosed in Finning’s Q1 2026 results, centres on fleet renewal and digital support rather than life-extension of legacy units. For mine planners and maintenance teams, the scale and timing signal a shift towards a modernised, OEM-supported truck fleet ahead of full production ramp-up.

    MAX Power’s Lawson hydrogen project expansion: scale and infrastructure lens for engineers
    Mining
    1 day ago

    MAX Power’s Lawson hydrogen project expansion: scale and infrastructure lens for engineers

    MAX Power Mining has secured an additional 155,125 acres (628 sq. km) of permits contiguous with its 1,224 sq. km Lawson natural hydrogen project in south-central Saskatchewan, creating the newly named Aurora project on a basement-controlled structural play along the Paleoproterozoic–Archean contact of the Sask Craton. The company has now accumulated 660,263 acres (2,672 sq. km) of provincial permits across the Genesis Trend while running a multi-well commercial validation drill programme at Lawson targeting large-scale natural hydrogen. An MOU with the City of Moose Jaw links potential hydrogen development to a nearby heavy industrial and major data centre corridor, signalling early focus on local offtake and infrastructure integration.

    American Mineral Resources’ diversified portfolio: capex and jurisdiction risk lens
    Mining
    1 day ago

    American Mineral Resources’ diversified portfolio: capex and jurisdiction risk lens

    American Mineral Resources is assembling a seven-jurisdiction portfolio across Quebec, British Columbia, Yukon, Chile, New Zealand, Western Australia and Tanzania, with its Piscau North polymetallic project in Quebec earmarked for a separate Canadian Securities Exchange listing, as it targets a Nasdaq uplist within 12 months via the OTCQB. CEO Ryan Cunningham is prioritising projects with existing permits or modest capex and argues that jurisdictional risk now rivals grade, citing Quebec’s Gaspé oil drilling ban as a warning. He also points to Canada’s flow-through share regime as a key financing advantage over US markets still fixated on AI and tech.

    Related Industries & Products

    Mining

    Geotechnical software solutions for mining operations including CMRR analysis, hydrogeological testing, and data management.

    CMRR-io

    Streamline coal mine roof stability assessments with our cloud-based CMRR software featuring automated calculations, multi-scenario analysis, and collaborative workflows.

    HYDROGEO-io

    Comprehensive hydrogeological testing platform for managing, analysing, and reporting on packer tests, lugeon values, and hydraulic conductivity assessments.

    GEODB-io

    Centralised geotechnical data management solution for storing, accessing, and analysing all your site investigation and material testing data.

    AllGeotechnicalMiningInfrastructureMaterialsHazardsEnvironmentalSoftwarePolicy